Ground Improvement Services Strengthen Site for LNG Terminal Expansion
Location
Gulf Coast
Industry
LNG
Challenge
Prepare a major LNG terminal for expansion with geotechnical construction and ground improvement services
Our client’s goals included expanding an LNG terminal for three LNG trains, a common gas pre-treatment unit, and a dock. Before construction could begin, the ground needed improvement to support the complete turnkey natural gas liquefaction facility.
ENTACT’s ground improvement expertise meant a successful solution for our client, and a project that was completed under budget and ahead of schedule.
ENTACT Solution
Prior to stabilizing, we cleared and grubbed the site, constructed board access roads, and performed stabilization pilot tests to confirm correct soil solutions. Our in-house soil geotechnical and stabilization expertise enabled us to be nimble in finding the right solution and helping maintain project timelines.
Having our company-owned equipment ready to work for our client was key for reaching productivity objectives. In addition, our experienced crew met every challenge, including constructing a pneumatic system and custom-made conveyance boxes to deliver cement for ground improvement activities.
- Sitewide clearing and grubbing
- Constructed board access roads
- Conducted field stabilization pilot tests to confirm reagent dosage met site requirements
- Excavated and backfilled soil and other materials
- Installed reinforced concrete drainage culverts and outflow structures
- Performed in-situ stabilization from timber mats to accommodate heavy equipment
The Results
- Completed services under budget and ahead of schedule
- Excavated and hauled more than 925,000 cubic yards of soil and material from 26 cut areas
- Backfilled and compacted more than 1 million cubic yards of soil and material within 31 fill areas
- Stabilized more than 2,275,530 cubic yards of soft dredged sediment and fill soils
- All cement-improved soil and sediment achieved a minimum unconfined compressive strength of 25 psi in 28 days




