Brook Sediment Removal and Bank Soil Remediation
Remedial activities performed by ENTACT included the removal of impacted sediments
from within the stream bed and the adjacent bank, east and west of the stream
bed to pre-determined elevation or as directed by post excavation confirmatory
soil sampling. Stream bed sediments and bank soils were impacted with volatile
organic compounds (VOCs) resulting from historical site operations.
After removal of impacted sediment, the stream bed was backfilled to original
grade with compacted common fill placed to within 6 inches of final grade and
a 6 inch layer of 6 mm gravel to final grade. Approximately 80 lineal feet of
the stream bed subgrade was covered with a 40 mil HDPE geomembrane liner across
the stream width to prevent re-contamination of remediated areas from groundwater
influx. Riprap was manually installed in areas of the stream where the adjacent
bank was disturbed as toe protection.
Disturbed stream bank areas were restored with common fill and topsoil. Common
fill was placed in 6 inch compacted lifts from subgrade to within 6 inches of
final grade with the final 6 inches backfilled with topsoil. The restored areas
were disced and seeded with switchgrass, flat pea and red top seed mix. Seeded
areas were mulched and natural fiber erosion control matting installed on seeded
slopes. 12 inch diameter coir fiber logs were installed at the toe of the disturbed
banks and secured in place with wooden stakes. Once in place, plant plugs were
placed on the coir log spaced at 6 inch intervals. Plant plugs consisted of Swamp
Milkweed, Sweet Flag, Sedges, Joe-Pie Weed, Blueflag Iris, Rushes, Cardinal Flower,
Duck Potato and Bulrushes.
Tree and wetland shrub species located within the disturbed stream bank areas
were replaced at a 1:1 and 1:1.25 ratio respectively. Tree species included Sweet
Gum, Green Ash, Black Willow and Purpleosier Willow. Wetland shrubs included
Red Osier Dogwood, Highbush Blueberry, Silky Dogwood and Smooth Adler. Two inches
of mulch were placed around the perimeter of new plantings. Tree trunks were
staked and wrapped with translucent plastic tubes for protection.
The stream bed is considered a State Open Waterway. The adjacent banks were delineated
wetlands with intermediate wetlands value. Work within the stream bed and adjacent
bank was performed under authority of the state environmental authority, Land
Use Regulation Program, Statewide General Permit #4. |
River Sediment Removal
ENTACT completed design and removal activities to address PCB contaminated soils
on a former aluminum die-casting facility property and identified areas of
soils and sediments along an eight-mile segment of the south branch of this
river. Site activities included construction of a water treatment system
to treat water generated from dewatering of excavated soils/sediments; installation
of temporary levees to enable removal and off-site disposal of PCB identified
river sediment; removal and off-site disposal of floodplain soils and isolated
lowland area soils; and site restoration.


|