Large-Scale Excavation Project
ENTACT is performing excavation of approximately
960,000 cubic yards of chromium contaminated
soils and other materials, which are classified
as hazardous waste.
To enable removal activities to occur, ENTACT designed, constructed, and
is currently operating a vacuum well point and
deep well groundwater extraction
system to lower the groundwater elevation and water content of waste materials
as much as practicable. Additional activities include installation and abandonment
of observation wells, inclinometers, and piezometers, as well as protection
and abandonment of several existing monitoring wells. Site restoration will
include the supply, placing, and compacting of approximately 880,000 cubic
yards of imported backfill. |
NPL Site
ENTACT completed remedial action activities that included management and consolidation
of all on-site debris; decontamination and demolition of remaining smelter
buildings; asbestos abatement; UST removal; regrading 1.3 million cubic yards
of slag and soil (slag piles as large as 8.5 acres and up to 50 feet tall);
removal of impacted soil and sediment from the river riparian areas; and construction
of a 185-acre soil cover system over the entire site. Activities were completed
to prepare the property for mixed-use redevelopment. |